Preparing of PQR, WPS as per standards and project specifications.
Inspection of incoming materials of MOUNDEDB BULLET.
Conducting all PWHT cycles for both Piping & equipment.
Doubling and tripling circular seam fit up to be checked.
Weld visual inspection. Assuring proper follow up of WPS during welding
Witness of DP & MP testing, of Inner and Outer cell.
Witness of Pad Leak Test of Nozzles.
All NDT as per fabrication. PWHT for erection joint by Electric Coil Heating.
After completion of all erection joints, Nozzles, Manholes etc. Bullet releases for hydro-test. Inspection as per given design, drawing and joint design. Ensuring the welding is performed as per approved WPS with qualified welders. Performing fit-up inspection (misalignment, groove angle, root Opening, preheat requirements etc.) & final inspection of weld joints.
Performing inspection activities as per QC procedures.
Preparing of PQR, WPS as per standards and project specifications.
Qualifying welders as per ASME Section-IX.
Inspection of incoming materials.
Inspection as per given design, drawing and joint design.
Weld visual inspection.
Assuring proper follow up of WPS during welding.
Ensuring the welding is performed as per approved WPS with qualified welders.
Performing fit-up inspection (misalignment, groove angle, root Opening, preheat requirements etc.) & final inspection of weld joints.
Performing the daily welding inspection reports.
Preparing of Grouping weld joints as per WPS wise & Welder wise.
Following up of applicable NDT methods after welding.
Interpretation of RT films
Reviewing of MPT, DPT & UT Tests
Witnessing blasting and painting as per the specification
Maintaining and updating QC documents
Test Pack Review and line walk with clients prior to pressure testing.
Witnessing of Hydro/Pneumatic pressure tests
Review the PRE-HEATING, POST HEATING, PWHT procedure & chart.
Familiar about , Alloy steel, CS, LTCS & MS based materials and electrodes
Supervising & inspecting the field engineering activities in construction, Fabrication, welding works as per approved WPS, Hydro tests, Reinstatement.
Review of isometric Drawings P & ID
Familiar with base materials and consumable welding materials conform to the specifications
Following up the priority joints for required NDT as per procedure issued by client. Verification and documentation of Test & quality plans.
Responsible for preparing the test packages.
Preparing & maintaining the drawing and documents
Preparing the documents for the QC activities. Final Completion and compilation of QC document
| 1) Never Pay to someone for a job, test or interview. Be aware, if they ask you for job processing fees, training fees or advance payment to make your job secure, etc. |
| 2) Don't Share your personal bank details in any case. |
| 3) If anyone asks money for a job on qatarjobseekers.com please report us. |